News Flash

Home

Posted on: August 16, 2021

City Construction Projects

Construction updates for the week of July 3

RDIIA – Conveyance Sewer along 7th St & Ramsdell St

Past week

  • Installed storm sewer on 7th Street and Ramsdell Street
  • Began installing sanitary sewer along Ramsdell Street from 7th Street to 6th Street

 Upcoming week

  • Construct water main on Ramsdell from 7th Street to 6th Street
  • Install storm sewer on the north side of 7th Street

 

RDIIB – Treatment Facility

This past week

  • Testing and start-up for new chemical equipment
  • Performed owner training of chemical equipment
  • Wrapped up miscellaneous electrical work within headworks building

 Upcoming week 

  • Grading parking lot and driveways around headworks building 
  • Paving around the headworks building tentatively next week

 

2022 12th Street Improvements

This past week

  • Completed installing storm catch basins and 12-inch storm sewer on 12th Street
  • Backfilled structures and pipe trenches to sand grade in preparation for constructing the road

 Upcoming weeks

  • Begin trenching and widening in areas without storm sewer on 12th Street

 

2022 Street Improvements - Quincy & Cleveland 

This past week

  • No work this week

 Upcoming weeks

  • Contractor waiting for back ordered materials to begin construction
  • Tentative start at end of July or early August

 

2022 Memorial Drive Reconstruction 

This past week

  • Pre-construction meeting with the contractor to discuss start date and schedule

 Upcoming weeks

  • Tentative start date of July 20th 

 

DWAM Grant Hydro-Excavation

This past week

  • Completed all hard surface hydro-excavations and backfilled with temporary gravel

 Upcoming week 

  • Returning the week of July 11th to restore all hard surface areas

 

Water Tower Improvements

This past week

  • No work this week

 Upcoming weeks

  • Kick-off meeting for Industrial Tower work

 

Municipal Roofing Project

This past week

  • Completed work at Water Works building, waiting for final approval and inspection

 Upcoming weeks

  • Punchlist items and site clean-up
  • Repair leaks/ items from inspections

 

Municipal Marina Dock Replacement Phase II

Upcoming weeks

  • Finish punch list items
  • Install remaining bumpers when they are delivered (back-order)

 

Riverbank Damage Bank Erosion

Upcoming weeks

  • Monitoring vegetation growth

 


Facebook Twitter Email