News Flash

Home

Posted on: August 16, 2021

City Construction Projects

1_Notice

Construction updates for the week of November 28

RDIA – Lining

This past week

  • No work was performed this past week

 Upcoming week

  • Contractor will not be on site; waiting for materials to be delivered

 

RDIIA – Conveyance

This past week

  • 48-inch sanitary sewer pipe construction continued toward the north-west near 7th & High

 Upcoming week

  • Continue constructing sanitary sewer toward the corner of 7th Street & High Street
  • Install Manhole 44
  • Start constructing sanitary sewer on 7th toward Engelman St

 

RDIIB – Treatment Facility

This past week

  • Forming grade beam for tank 2 
  • Installed Headworks Building roof planks
  • Installed remaining storm sewer
  • Installed temporary doors on headworks 

 Upcoming week

  • Tank No.2 grade beam re-steel
  • Start Vactor Pit construction
  • Temporary handrails around headworks roof

 

Riverbank Erosion & Riverwalk repairs

This past week

  • Topsoiled and seeded remaining restoration areas
  • Site clean-up

 

2021 Streets (Jackson, Van Buren, Jefferson, 8th Street)

This past week

  • Removed signs, demobilized from site

 

Municipal Roofs

This past week

  • No roofing work was completed due to the weather and waiting on materials 

 Upcoming week

  • Walking pads and drain fixed for City hall
  • Remaining work on City Hall, and well houses will be postponed until spring

 

Municipal Marina Dock Replacement Phase II

This past week

  • No work has started, Contractor waiting on barge to complete another project

 Upcoming week

  • No work scheduled, Contractor waiting on barge to complete another project

Facebook Twitter Email

Other News in Home