News Flash

Home

Posted on: August 16, 2021

City Construction Projects

Construction updates for the week of June 26

RDIIA – Conveyance Sewer along 7th St & Ramsdell St

Past week

  • Installed last sections of 48-inch sanitary sewer on 7th Street between Kosciusko to Ramsdell Streets
  • Dewatering storm sewer

 Upcoming week

  • Constructing sanitary sewer on Ramsdell Street from 7th to 6th Streets

 

RDIIB – Treatment Facility

This past week

  • Performed equipment startup tests for headworks building
  • Contractor/manufacturer performed training sessions with City on new equipment
  • Pulled wiring through conduits to new drives
  • Poured concrete approach slab for the vactor pit
  • All tanks filled for completion of weep testing

 Upcoming week 

  • Test chlorination system
  • Miscellaneous electrical work
  • Grade driveway and parking areas around headworks building
  • Continue clean-up of the site

 

2022 12th Street Improvements

This past week

  • Installed storm catch basins and 12-inch storm sewer

 Upcoming weeks

  • Complete constructing storm sewer and drainage structures
  • Begin clearing site of spoils

 

2022 Street Improvements - Quincy & Cleveland 

This past week

  • No work this week

 Upcoming weeks

  • Contractor waiting for back ordered materials to begin construction
  • Tentative start at end of July or early August

 

2022 Memorial Drive Reconstruction 

This past week

  • Pre-construction meeting with the contractor to discuss start date and schedule

 Upcoming weeks

  • Tentative start at the end of July

 

DWAM Grant Hydro-Excavation

This past week

  • Completed all hard surface hydro-excavations and backfilled with temporary gravel

 Upcoming week 

  • Returning the week of July 11th to restore all hard surface areas
  • Finishing all hydro-excavations the week of July 11th, along with the hydro-excavations within US-31

 

Water Tower Improvements

This past week

  • Final walkthrough of the Maywood Tower painting
  • Started refilling the Maywood Tower

 Upcoming weeks

  • Continue filling the Maywood Tower
  • Start disinfection process

 

Municipal Roofing Project

This past week

  • Completed roofing work at the Firehall
  • Completed flag pole work at the Ramsdell

 Upcoming weeks

  • Start work on roof for the Water Works building

 

Municipal Marina Dock Replacement Phase II

Upcoming weeks

  • Finish punch list items
  • Install remaining bumpers when they are delivered (back-order)

 

Riverbank Damage Bank Erosion

Upcoming weeks

  • Monitoring vegetation growth


Facebook Twitter Email