Construction updates for the week of May 14
2023 Street Improvements - S. Lakeshore Drive
This Past week
- Gravel shoulders were placed, shaped, and compacted
- Ditches were fine graded
- The project area was cleaned up
- Concrete foundation for the new streetlights were installed
- Pavement markings for the existing beach house parking lot, new parking lot, new parking areas, and roadway were all completed
Upcoming weeks
- Installing new signage and split rail fencing
- Waiting for delivery of new street lights
2022 Street Improvements – Quincy & Cleveland
This past week
- Poured driveway approaches and remaining sidewalk
- Paved the top course of asphalt on Quincy and Cleveland streets
- Adjusted catch basin castings
- Worked on slope restoration and overall site clean-up
Upcoming weeks
- Raising manhole castings and pouring concrete collars
- Chip out and repair the concrete collars in the Quincy/Washington intersections
- Continue working on slope restoration and seeding
- Consumer’s Energy/ATT to relocate pole at intersection of Quincy/Cleveland
8th and Vine intersection
Upcoming weeks
- Intersection closure to repair manhole concrete collars (schedule TBD)
S. Lakeshore Drive Water Main
This past week
Upcoming weeks
- Working with directional drilling contractor to schedule construction of new water main loop from Douglas Park dog-park to Harbor Drive